CERC Accepts Inadvertent Delay, Asks NLDC to Issue Pending RECs to a Cogeneration Project

The company had delayed the filing of the application for the issuance of RECs by four days

thumbnail

Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights


In its latest order, the Central Electricity Regulatory Commission (CERC) has asked the National Load Despatch Center (NLDC) to accept the request put forth by Balrampur Chini Mills for the grant of renewable energy certificates (RECs) for February 2018.