Delay in Setting up Transmission System for Solar Projects will Now Attract a Penalty

Solar park development agency will attract a penalty of ₹ 1,000/day in case of such delays

thumbnail

Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights


According to the latest notification issued by the Ministry of New and Renewable Energy (MNRE), any delay in the scheduled commissioning date of solar projects due to unavailability of internal execution or transmission system by solar park developers will now be liable to a penalty.