The petitioner cited multiple unforeseen issues that led to the delay in commissioning

thumbnail

Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights


The Gujarat Electricity Regulatory Commission (GERC) has granted a 315-day extension for commissioning a transmission line, along with bays and a metering system, to evacuate 30 MW of power from a wind-solar hybrid project in Jafrabad, Gujarat.