Karnataka Regulator Reduces Tariff for 60 MW of Adani Green’s Delayed Solar Projects

The Commission lowered tariff to ₹4.36/kWh for the projects, down from ₹4.84/kWh and ₹4.82/kWh

September 18, 2020

thumbnail

Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights


The Karnataka Electricity Regulatory Commission (KERC) has denied Adani Green Energy (UP) Limited’s requests for relief under the force majeure clause of its power purchase agreement (PPA) with the Bangalore Electricity Supply Company Limited (BESCOM). The clause was invoked for delays in the completion of 60 MW of solar projects in the state.