MERC Orders Arbitration to Resolve Delayed 500 MW Solar Project Dispute

The project’s scheduled commercial operation date was March 31, 2024

thumbnail

Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights


The Maharashtra Electricity Regulatory Commission (MERC) has directed the Maharashtra State Electricity Distribution Company (MSEDCL) and the Braithwaite Nacof Solar Project (Braithwaite) to resolve a power purchase agreement (PPA) dispute through arbitration.