Regulator Rules in Favor of Captive Wind Developer, Marks Down Transmission Charges

The wind generator to pay inter-DISCOM transmission charges only for 8.8MW out of 25.6 MW

March 4, 2022

thumbnail

Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights


The Andhra Pradesh Electricity Regulatory Commission (APERC) recently ruled that a wind project developer was liable to pay inter-DISCOM (distribution company) transmission charges for 8.8 MW out of the total capacity of 25.6 MW up to October 15, 2020, when the amendment to long-term open access (LTOA) was approved.