Regulator Rejects Solar Developer’s Petition for Refund of Liquidated Damages

The Commission noted that the defaulting party is liable to pay the liquidated damages in case of non-supply of energy

thumbnail

Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights


The Karnataka Electricity Regulatory Commission (KERC), in a recent order, has rejected the petition of Kavit Green Energy asking Gulbarga Electricity Supply Company Limited (GESCOM) to refund ₹28.3 million (~$380,087) deducted as liquidated damages for delay in commissioning a 5 MW solar project.