Regulator Rejects Wind Developer’s Plea for Adjustment of Banked Units

The Commission directed DISCOM to refund wheeling and transmission charges

February 1, 2023

thumbnail

Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights


Maharashtra Electricity Regulatory Commission (MERC) has ruled that a wind power generator was not entitled to an adjustment of banked units from the generating project as the banked units injected into the grid and the open access availed during the same financial year were from different generating stations.