ReNew Power Fined for Project Commissioning Delay but PPA Not Terminated

The Supreme Court has asked ReNew Power to pay ₹119 million for delay in project commissioning

thumbnail

Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights


The Supreme Court of India has asked renewable energy project developer ReNew Power to pay a penalty of ₹119 million (~$1,827,700) to the Madhya Pradesh Power Management Company Limited (MPPMCL) for delaying the commissioning of a solar project in the state by more than 210 days.