MERC Rejects Plea to Extend Commissioning Date of 200 MW Solar Project

The Maharashtra Electricity Regulatory Commission (MERC) has rejected a solar power developer’s request to extend the scheduled commercial operation date (SCOD) for its...

October 5, 2026

/

Rakesh Ranjan

/

Markets & Policy

,

Solar
thumbnail
MERC Allows Time Extension for Solar Projects Facing Transmission Delays

The Maharashtra Electricity Regulatory Commission (MERC) has allowed, in principle, a petition seeking revision of the scheduled commencement of supply dates (SCSD) for...

October 5, 2026

/

Arjun Joshi

/

Markets & Policy

,

Solar
thumbnail
Gujarat Regulator Rejects Captive Solar Project’s Time Extension Plea

The Gujarat Electricity Regulatory Commission (GERC) has rejected a petition seeking an extension to complete the evacuation infrastructure for a 9 MW captive solar...

September 18, 2026

/

Arjun Joshi

/

Markets & Policy

,

Solar
thumbnail
MNRE’s West Asia Advisory Offers More Time, but Developers Say Relief May Fall Short

The Ministry of New and Renewable Energy’s (MNRE) recent advisory for renewable energy projects offers some relief to developers grappling with equipment supply,...

September 18, 2026

/

Rakesh Ranjan

/

Mercom Research Focus

,

Renewable Energy
thumbnail
Standalone Solar Module Makers Seek 18-Month ALMM List-II Extension

The All India Solar Module Manufacturers (AISMM) has urged Union Minister for New and Renewable Energy (MNRE) Pralhad Joshi to provide an 18-month, output-linked...

July 23, 2026

/

Arjun Joshi

/

Manufacturing

,

Solar
thumbnail
MNRE Sets DCR Portal Route for ALMM List-II Extension Requests

The Ministry of New and Renewable Energy (MNRE) has directed renewable energy developers to submit requests for exemption from compliance with the Approved List of...

June 1, 2026

/

Rakesh Ranjan

/

Markets & Policy

,

Solar
thumbnail
MNRE Extends Solar Park Program Until March 2029

The Ministry of New and Renewable Energy (MNRE) has extended the timeline of the ‘Development of Solar Parks and Ultra Mega Solar Power Projects’ program by three years...

September 19, 2025

/

Staff

/

Market & Policy

,

Solar
thumbnail
MNRE Extends BIS Compliance Deadline for Over 200 kW Solar Inverters

The Ministry of New and Renewable Energy (MNRE) has extended the deadline for solar inverters of more than 200 kW capacity to conform to the Bureau of Indian Standards...

August 8, 2025

/

Melvin Mathew

/

C&I

,

Energy Storage

,

Markets & Policy

,

Solar
thumbnail
Gujarat Regulator Grants 343-Day Extension for 70 MW Wind-Solar Project

The Gujarat Electricity Regulatory Commission (GERC) has granted a 343-day extension for a 70 MW wind-solar hybrid project to establish its evacuation infrastructure,...

June 30, 2025

/

Arjun Joshi

/

Grid

,

Market & Policy
thumbnail
As ISTS Waiver Nears End, Developers Need Extension Amid Lack of Substations

As the deadline for the Inter-State Transmission System (ISTS) charges waiver approaches, additional substations are critical to ensure the smooth facilitation of...

April 16, 2024

/

Gautamee Hazarika

/

Markets & Policy

,

Mercom Research Focus

,

Solar
thumbnail
Rajasthan Regulator Allows Five-Year Extension on Expired PPAs for Wind Projects

The Rajasthan Electricity Regulatory Commission (RERC), in a recent order, granted approval to Rajasthan Urja Vikas Nigam (RUVNL) to extend the power purchase agreements...

September 25, 2023

/

Rakesh Ranjan

/

Other

,

Wind
thumbnail
MNRE Extends Timeline for Ultra Mega Solar Park Program by Two Years

The Ministry of New and Renewable Energy (MNRE) has extended the timeline for the ‘Development of Solar Parks and Ultra Mega Solar Power Projects’ program to March 31,...

June 20, 2023

/

Satish Shetty

/

Markets & Policy

,

Solar
thumbnail
Developer can Sell Solar Power in Open Market Post Commissioning Date: CERC

The Central Electricity Regulatory Commission (CERC) recently ruled that a solar developer was not obligated to supply the commissioned capacity of 62.5 MW after the...

June 6, 2023

/

Rakesh Ranjan

/

Markets & Policy

,

Solar
thumbnail
Daily News Wrap-Up: MNRE Revokes Blanket Extension for RE Projects in GIB Area

The Ministry of New and Renewable Energy has revoked its order granting an extension of 30 days for the commissioning of renewable energy projects, for which the...

June 6, 2023

/

Mercom Staff

/

Daily Wrap-up
thumbnail
MNRE Revokes Blanket Extension for Renewable Energy Projects in the GIB Area

The Ministry of New and Renewable Energy (MNRE) has revoked its order granting an extension of 30 days for the commissioning of renewable energy projects, for which the...

June 5, 2023

/

Rakesh Ranjan

/

Markets & Policy

,

Solar