Two Solar Projects Citing ‘Force Majeure’ Get Commissioning Deadline Extension

The heavy rainfall in north Karnataka in 2019 constituted a 'force majeure' event

thumbnail

Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights


The Karnataka Electricity Regulatory Commission (KERC) recently condoned the delay in commissioning two solar projects of 20 MW each. It extended the scheduled commercial operation dates for both the projects on account of a ‘force majeure’ event.